Does anyone knows about a strange behaviour of the calender scheduler tool after the upgrade from the 2018 SF to the 2020 SF.

See the screeshots below. The 1st screenshot is our production server. Application generated with the SF 2018.2

The 2nd screenshot is the same function generated with the SF of 2020.2.

The resources are now columns in stead of rows on the left hand side.

The tasks are now columns.
The time is transformed to row, which normally are the resources.

And normally the time was horizontal - as a zoom-in of the date.
But now the date and the time are become columns and rows?

 

 

 

Hi Edwin,

Since a recent version of the Windows/Web GUI, the Scheduler now supports all view types. The view types that are named in the Extender settings are now visible. The view type of your first screenshot is called 'Timeline’ and only works if it's the only view type assigned to the Extender.

If your only View type is Timeline, your first screenshot overview is restored.

Hope this helps!,

Mark Jongeling


Thanks I’m gonna check that out.


I was struggling starting the end-user application after changing the model. But it does start now. I deleted all the other view types, and the scheduler/timeline looks good now.