I have enabled two tasks with double click on the same subjects. Both tasks are configured with a different double click column. This seems to work as intended (at least when running the Universal GUI directly on the SF).
However the SF gives a validation warning that multiple grid double click tasks are not supported (val_multiple_grid_double_click_tab). It says the consequence is that only the first task will be used. I noticed that this validation message doesn’t check the double click column.
Could this validation message be outdated or incomplete (not including the double click column)?
I’m using the latest version of the full platform.