If I want to run a task every minute of every day. 

What is the starting at and ending at? 

00:00:00 is not allowed, so is this 12:00:00 AM or PM?

and if you do from 12:00:00 AM to 12:00:00 AM (or PM) it treats it as a once a day schedule it appears instead of every minute.  

Best answer by Mark Jongeling

Hi Freddy,

You can set the starting at 12:00:00 AM and the ending at 11:59:59 PM, this will ensure the schedule will have runs for the whole day.

Example:

Process schedule

 

View original
Did this topic help you find an answer to your question?
This topic has been closed for replies.

Freddy
Forum|alt.badge.img+16
  • Thinkwise Local Partner Brasil
  • February 3, 2023
Mark Jongeling wrote:

Hi Freddy,

You can set the starting at 12:00:00 AM and the ending at 11:59:59 PM, this will ensure the schedule will have runs for the whole day.

Example:

Process schedule

 

 

Thanks, why not make that a 24 hour time scale?  Makes it a bit more clear. Or even make the start/stop time optional..  so your recurring value per definition runs the whole day. 


Mark Jongeling
Administrator
Forum|alt.badge.img+23

Hi Freddy,

You can set the starting at 12:00:00 AM and the ending at 11:59:59 PM, this will ensure the schedule will have runs for the whole day.

Example:

Process schedule

 