Hi !

We have 2 tables Employee and Invoice. Adding rows to them is done with this 2 process flows: add_employee , add_invoice.
Start table task for add invoice flow has a parameter with lookup to employee table :
 

 

In the new opened popup we start the add_employee flow. Unfortunately it stops running at a start task process action with no status code for debugging in the “process_flow_monitor”, al so there is no error in “live_error_log”.


 

 

After canceling the start table task for the add_invoice flow the add_invoice show up in the monitor.

 

 

The add_employe process looks like this:

 

 

Any idea why is this happening?

 

PS:
For now we used a workaround and executed the functionality of the task in the decision preceding the start task process flow.

Best answer by Erwin Ekkel

Some additional questions:

  • I assume this is a template task and not a gui or windows command task? 
  • Also did you check f12 and the normal error log for any errors? 
  • Does that task work if you execute it on the database, or if you execute it in the gui without the process flow? 

It seems like the process flow is failing on the actual execution of the task since it’s not able to finish the task. For testing purposes you could set the code in the task in comments to see if the flow continues when the task doesn’t have any code to execute.

View original
Did this topic help you find an answer to your question?
This topic has been closed for comments

2 replies

Forum|alt.badge.img+17
  • Moderator
  • 761 replies
  • Answer
  • January 20, 2025

Some additional questions:

  • I assume this is a template task and not a gui or windows command task? 
  • Also did you check f12 and the normal error log for any errors? 
  • Does that task work if you execute it on the database, or if you execute it in the gui without the process flow? 

It seems like the process flow is failing on the actual execution of the task since it’s not able to finish the task. For testing purposes you could set the code in the task in comments to see if the flow continues when the task doesn’t have any code to execute.


Jeroen van den Belt
Administrator
Forum|alt.badge.img+9

Hi ​@Ionut_Catalin,

Do you have any updates for us based on Erwin's questions above?


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings