Large process flow becomes unstable during fast user interaction

  • July 3, 2026
  • 1 reply
  • 34 views

Forum|alt.badge.img+1

Hello,

We are experiencing an issue with the following process flow, see attachment. As you can see, it is a very large process flow, but in general it does return the correct results and performs the expected actions.

However, when I quickly click through the process, open and close the task, etc., basically when I interact with it a bit faster, it starts to behave unexpectedly. For example, an intermediate screen sometimes no longer opens. In addition, cancelling also takes quite a long time, around 10 seconds.

Could this behavior be caused by the process flow being too large, for example because the flow has not fully completed yet before a new start is triggered? Or is there likely something else going on?

Our preference would be not to split up the process flow, as this would require a lot of work and would also introduce additional risks. Therefore, we would first like to understand whether there is another way to make this process more stable.

1 reply

I don’t think the size of the process flow is the problem here. I’ve seen flows 4 or 5 times the size of this one working like a charm. 

I would expect either the process flow is cancelled haflway through or an error occurs. What information does the processflow monitor and F12 (debug tools) give you one this?