We try to set up a drag-drop scenario within the Universal GUI.

The main goal is to place outstanding orders in the planning (scheduler) with a drag & drop task from a detail table.

Because drag-drop from card lists is not yet available, we make use of a grid with a multiline HTML field as only visible field as source table. The target table makes use of the scheduler component.

Questions/wishes:

1. How can the activity resource of the target table be linked to the drag-drop task?


2. Can week numbers, dates and times be optimized?



 


2 replies

Userlevel 4
Badge

@Harm Horstman I've looked into the dragging onto the resource and I'm not sure how you are trying to configure it, but i think this does not work. Could you please create a ticket with Thinkwise?

About the translation of the months we are bit confused, because when we change the users language through the user preference dialog, these get translated just fine.

Also the AM/PM is very strange, we hard coded it to use military notation. Could you make a ticket for this to and provide the configuration of the scheduler and version of Universal. We must have overlooked some case.

Userlevel 5
Badge +20

Hi @Sebastiaan Meijerink,

I have made a ticket (9312S) for this.



 

 

Reply