Hi,
I am wandering what the best practice is when upgrading Thinkwise itself in an DTAP setup. At the moment we are using 2024.1.13 in all deployments (on Azure, but different physical locations for P). The goal is to update all environments with the latest stable version and will be done over a limited period of time, but could still take a couple of weeks.
When I upgrade the D first, will I still be able to service the older versions with updates? If so, I can go from D to T to A to P.
When I am not able to service older version, what would be the approach in that case?