Hi,

I am wandering what the best practice is when upgrading Thinkwise itself in an DTAP setup. At the moment we are using 2024.1.13 in all deployments (on Azure, but different physical locations for P). The goal is to update all environments with the latest stable version and will be done over a limited period of time, but could still take a couple of weeks.

When I upgrade the D first, will I still be able to service the older versions with updates? If so, I can go from D to T to A to P.

When I am not able to service older version, what would be the approach in that case?

@Robert Wijn 2 Assuming you are talking about the Runtime components here (Indicium & Universal): different versions on different environments works fine! Basically a Platform version (f.e. 2024.3) works with any Indicium & Universal version equal to or higher than the Platform version (2024.3.10 and up, including 2025.1.X versions). 

Note that Indicium and Universal versions could be dependent on each other, so it is recommended to keep those versions aligned as much as possible.

Does this answer your question?


Hi Arie,

That does answer my question. It will be no problem to keep the Universal and Indicium aligned per deployment environment.

Thanks !