relations between tasks in resource scheduler

Related products:Windows GUI
  • November 10, 2020
  • 4 replies
  • 19 views
Marius Korff
  • Marius Korff
    Marius Korff

In the activity scheduler it is possible to show relations between the tasks, in the resource scheduler this is not yet possible (the extender properties are included though).

I have a situation where multiple tasks have to be performed by multiple resources, and it can be difficult to distinguish which tasks belong together.

It would be great to be able to show the dependencies of tasks, possibly the same way the activity scheduler does.

Did this topic help you find an answer to your question?

4 replies

Roel
Vanguard
Forum|alt.badge.img+2
  • Vanguard
  • 92 replies
  • November 10, 2020

Hey Henk Jan,

 

Thanks for the suggestion. A POC has already been made so we should be able to implement this in the near future. We will keep you posted in this thread.

 

Kind Regards,

Roel


Jasper
Superhero
  • 678 replies
  • December 9, 2020
Updated idea status NewOpen

Roel
Vanguard
Forum|alt.badge.img+2
  • Vanguard
  • 92 replies
  • February 2, 2021

Hello,

 

This feature is now implemented. If you use the Parent task id column in the extender you can now link the appointments, which looks like this:

 

 

This feature is implemented in GUI version 2021.1.13.

 

Kind Regards,
Roel


Roel
Vanguard
Forum|alt.badge.img+2
  • Vanguard
  • 92 replies
  • February 2, 2021
Updated idea status OpenCompleted

Reply


Cookie policy

We use cookies to enhance and personalize your experience. If you accept you agree to our full cookie policy. Learn more about our cookies.

 
Cookie settings